|
|
|
|
|
|
|
 |

St. Matthews Cathedral Restored 31 Page Booklet now available!
|
|
History of the Restoration
|
Since
the St. Matthew’s Cathedral
cornerstone was laid in 1893,
time and weather took
a heavy toll on its roof, support
structure and interior. Culprits
included airborne pollution,
wind, water, snow and ice. These
same elements caused the
deterioration and need for recent
restoration of the U.S. Capitol
and Library of Congress. In
1998, our architect and structural
experts said the existing dome
and roof would be safe only
until the year 2000.
The Cathedral’s first complete
restoration began in 2000 and was
completed by September 21, 2003, the Feast
of St. Matthew the Apostle. What follows is
a synopsis of the work.
|
| Exterior
|
Dome.
One hundred ninety feet from
ground level at the top, the
dome has been completely renewed.
The pitted and eroded copper
was removed and and rotted wood
was replaced. A protective membrane
was applied before the new copper
was installed.
Roof.
The original slate had outlasted
its life expectancy of 70 years
by more than 30 years. Many
pieces were worn, brittle and
cracked. These too, have been
replaced with new slate, also
with a waterproof membrane underneath.
Façade.
Its ability to withstand the
elements was compromised by
unstable mortar joints, cracked
terra cotta, loose brick, and
rusted steel window frames.
The mortar joints have been
repointed. |
| Interior |
Mosaics
and Marble.
Craftsmen repaired and
cleaned the central sanctuary
mosaics. In some places, the
mosaics had separated from
the wall. The marbles and ceilings
were restored in the sanctuary,
Blessed Sacrament Chapel, Wedding
Chapel and Angels' Chapel. Work
then moved to the area above
the communion rail and mosaics
of the pendentives that depict
the four evangelists.
Murals.
Cleaning was required for the
accumulated incense, candle
residue, grime and dirt that
dulled and darkened the
luster and brilliance of the
murals. These bright colors can now be seen for the first time in many years.
Ceiling.
The ceiling was restored
to correct an unsound support
system. Wood framing showed signs
of stress and some of the plaster coffers
had moved and cracked.
Water was responsible for blistering
paint and damage to the major
arches. Ceiling elements were repaired and, in some cases, replaced.
Fire
and Safety. Some
electrical circuitry and wiring
dated to 1895 and was replaced
to avoid the possibility of
fire. Some original
wiring was minimally insulated, jacketed with cotton and
subject to fiber rot and abrasions.
Since interior wood and plaster are
highly combustible, enhanced
fire and safety measures were mandatory.
Plastering
and Repainting. Water-damaged
plaster and blistering paint
were removed in several
chapels. These areas were then plastered and painted.
Lighting
and Organ. New lighting
was installed so that visitors
can now clearly see the restored
mosaics, murals, ceiling and
other features of the interior.
The new organ, installed beginning
in 1995, will eventually be completed,
doubling its number of pipes
to its full complement of 5,045.
If you would like more information
about the Cathedral Restoration
Project
please contact Nancy House
at (202) 347-3215 x512.
|
|
|
Restoration Photo Gallery |
|
CLICK HERE TO VIEW A SLIDE SHOW |
| CLICK
ON THE IMAGES BELOW TO
ENLARGE |
 |
 |
 |
 |
Denka
Used to Inspect
Interior
03/23/98 |
Original
Copper Dome With
Scaffolding
02/17/00 |
New
Copper Applied to
Dome
03/08/00 |
Dome
With New Copper
05/08/00 |
 |
 |
 |
 |
New
Dome Covering is
Complete
10/13/00 |
Gilding
Cross
05/28/01 |
New
Slate Applied to
Roof
07/03/01 |
Sanctuary
Mosaic Restoration
12/07/01 |
 |
 |
 |
 |
Cleaning the Sanctuary Mosaic
of St. Matthew
02/08/02 |
Restoring a
Sanctuary Ceiling
Rosette
03/15/02 |
Preparing
Paints, Blessed
Sacrament Chapel
04/23/02 |
Restoring a
Mural in the Blessed Sacrament
Chapel
04/23/02 |
 |
 |
 |
 |
Work
on Plaster Arch,
Wedding Chapel
07/16/02 |
Restoring
Arch, Wedding Chapel
08/20/02 |
Scaffolding
in the Nave
08/20/02 |
Restored
Mosaic in the St. Anthony
Chapel
09/12/02 |
 |
 |
 |
 |
Scaffolding in the St. Anthony Chapel
09/20/02 |
Testing the
'Calling of St.
Matthew' Mural
09/26/02 |
Removing
Scaffolding in the Sanctuary
11/06/02 |
Restored Ceiling in the Blessed
Sacrament Chapel
11/06/02 |
|
 |
 |
 |
Scaffolding
in the
Dome
12/12/02 |
Electricians
Install New Lighting
in the Dome
03/06/03 |
The
Restored Dome
04/03/03 |
 |
 |
 |
Restoration
of 'The Martyrdom
of St. Matthew' Mural
03/06/03 |
The 'Martyrdom
of St. Matthew'
Mural Restored
05/16/03 |
'The
Calling of St. Matthew'
Mural Before Restoration
12/12/02 |
 |
 |
 |
Restoring
the Ceiling in Our
Lady's Chapel
04/03/03 |
Our
Lady's Chapel Restoration
04/03//03 |
Cleaning
the Mosaics in Our
Lady's Chapel
05/05/03 |
 |
 |
 |
Scaffolding in the
Nave
04/24/03 |
Preparing
to Clean the Nave Ceiling
and Mural
05/16/03 |
St. Anthony's
Chapel Viewed from Our
Lady's Chapel
04/24/03 |
 |
 |
 |
Cleaning
the Mural 'Saintly
and Eminent Personages
of the Americas'
07/03/03 |
A
Close-up of 'Saintly
and Eminent Personages
of the Americas'
04/03/03 |
Painters
Detailing 'Saintly
and Eminent Personages
of the Americas'
07/03/03 |
 |
 |
 |
Restoring
a Mural in the
St. Francis Chapel
05/29/03 |
The
Restored Mural above the Altar in the St. Francis
Chapel
05/29/03 |
The
Restored Mural
on the North Wall
of the St. Francis
Chapel
05/16/03 |
 |
 |
 |
Electricians
Work on a Mock-up
of the New Light
Fixtures
07/03/03 |
The
Restored Sanctuary
on Easter Sunday
04/20/03 |
'The
Calling of St. Matthew'
Mural Restored
03/06/03 |
|
|
|
|
|
|
|
|
|
Cathedral
of Saint Matthew the Apostle
1725 Rhode Island Avenue, NW
Washington, DC 20036
Phone: (202) 347-3215 Fax: (202) 347-7184
email: cathstmatt@stmatthewscathedral.org
|